=== page 1064 === 49.105-1 FEDERAL ACQUISITION REGULATION (7) Plans for transferring title and for delivering to the Government any materials the Government needs. (8) Basic rules and procedures for protecting, preserving, and getting rid of contractor and subcontractor termination inventories, including preparing termination inventory schedules. (9) Contractor accounting practices and preparation of SF 1439 (Schedule of Accounting Information (49.602-3)). (10) What form to use when submitting settlement proposals. (11) Accounting review of settlement proposals. (12) Any need for interim financing through partial payments.; (13) Rough timeline for negotiating the settlement, including when the contractor and subcontractors must submit settlement proposals, termination inventory schedules, and accounting information schedules (see 49.206-3 and 49.303-2). (14) Actions taken by the contractor to reduce harm to employees hurt by the termination (see paragraph (g) of the letter notice in 49.601-2). (15) Contractor's duty to provide accurate, complete, and current cost or pricing data, and to certify this data (see part 15 requirements for certified cost or pricing data) when the termination settlement amount, or partial termination settlement amount plus the estimated cost to complete the continued work, exceeds the cost or pricing data threshold in part 15. 49.105-1 Release of excess funds. (a) The TCO must estimate funds needed for settlement, and within 30 days of receiving the termination notice, recommend that the contracting officer release excess funds. The contracting officer or TCO (if given the responsibility) should quickly release the initial excess funds. The TCO must not recommend releasing amounts under $1,000 unless requested by the contracting officer. (b) The TCO must continuously monitor funding requirements in order to release additional excess funds promptly. See 49.604 for a recommended format. If previous funding releases create a shortage for settlement, the TCO must tell the contracting officer immediately. The contracting officer must restore the funds within 30 days. 49.105-2 Cleanup of construction site. For terminated construction contracts, the contracting officer must direct cleanup actions to ensure: site cleanup, protection of usable materials, removal of hazards, and any other actions needed for a safe and healthy site. 49.106 Fraud or other criminal conduct. If the TCO suspects fraud or other criminal conduct related to the settlement of a terminated contract, the TCO shall discontinue negotiations and report the facts under agency procedures. 49.107 Audit of prime contract settlement proposals and subcontract settlements. (a) Prime contractor audits. The TCO must send settlement proposals to the audit agency for review when the value meets or exceeds the certified cost or pricing data threshold in part 15. The TCO may send proposals valued below the threshold for certified cost and pricing data for audit review. (1) When referring proposals, include(i) Specific information the TCO considers relevant; and (ii) Facts and circumstances to help the audit agency. (2) The audit agency must(i) Develop requested information; (ii) Make additional accounting reviews as appropriate; and (iii) Submit written comments and recommendations to the TCO. (3) For proposals under the threshold that do not need formal examination, the TCO will do a desk review and include a written summary in the termination case file. (b) Subcontract settlement audits. The TCO must refer subcontract settlements to the audit agency when— (1) The amount exceeds the certified cost or pricing data threshold; or (2) The TCO decides a complete or partial accounting review is advisable. The audit agency must submit written comments and recommendations to the TCO. This review does not remove the prime contractor's or higher-tier subcontractor's responsibility to do their own accounting review. (c) Contractor responsibilities. (1) Prime contractors and subcontractors must perform accounting reviews and necessary field audits. However, the TCO should request a Government audit of a subcontractor’s settlement proposal when— 49.1-4