=== page 617 === Chapter 5 Availability of Appropriations: Time Another fast pay issue was discussed in B-203993-O.M., July 12, 1982, in which GAO’s General Counsel advised the GAO finance office that it could pay the invoice amount, without the need for further verification, if goods are shipped “f.o.b. [freight on board] origin” and the difference between the estimated price in the purchase order and the amount shown on the invoice is based solely on transportation costs. Any discrepancy regarding the transportation costs could be determined and adjusted through post-audit procedures under 31 U.S.C. § 3726. This would not apply to goods shipped “f.o.b. destination” because transportation charges are included as part of the purchase price. As a general proposition, since fast pay procedures permit the agency to dispense with prepayment voucher audits, GAO’s approval of fast pay procedures has been based on the assumption that the agency would conduct 100 percent post-payment audits. In 67 Comp. Gen. 194 (1988), GAO approved in concept a GSA proposal to combine fast pay procedures with the use of statistical sampling in post-audit for utility invoices. “We see no reason why these two techniques cannot be combined in appropriate circumstances if they result in economies and adequately protect the interests of the government.” Id. at 199. However, GAO found that the specific proposal did not provide adequate controls. GSA modified its proposal, and the Comptroller General approved it in 68 Comp. Gen. 618 (1989). 3. Lease and Rental Agreements The advance payment statute has been consistently construed as applicable to lease or rental agreements as well as purchases, and applies with respect to both real and personal property. 18 Comp. Gen. 839 (1939); 3 Comp. Gen. 542 (1924); B-188166, June 3, 1977. Thus, when the government acquires land by leasing, payments must be made “in arrears” unless the applicable appropriation act or other law provides an exemption from 31 U.S.C. § 3324. 19 Comp. Gen. 758, 760 (1940). The Federal Acquisition Regulation advance payment provisions do not apply to rent. 48 C.F.R. § 32.404(a)(1). In 57 Comp. Gen. 89 (1977), the Comptroller General held that a leasing arrangement of telephone equipment called “tier pricing,” under which the government would be obligated to pay the contractor’s entire capital cost at the outset of the lease, would violate 31 U.S.C. § 3324. See also 58 Comp. Gen. 29 (1978). Page 5-62 GAO-04-261SP Appropriations Law—Vol. I