=== page 209 === Chapter 16: Auditing and Validating the Cost Estimate An independent cost estimate (ICE) was conducted by a group outside the acquiring organization to determine whether other estimating methods produce similar results. An ICE should be performed by an organization outside of the program office’s influence. The depth of the ICE should be sufficient to allow for reconciliation between the ICE and the program office estimate, and differences between the two should be documented and justified. The ICE should be based on the same technical baseline and ground rules as the program office estimate. Without an ICE, decisions-makers will lack certain insights into a program’s potential costs because ICEs frequently use different methods and are less burdened with organizational bias. Moreover, ICEs typically incorporate adequate risk and, therefore, tend to be more conservative by forecasting higher costs than the program office. A program estimate that has not been reconciled with an ICE has an increased risk of proceeding underfunded because an ICE provides an objective and unbiased assessment of whether the program estimate can be achieved. For more information on comparing the cost estimate to an independent cost estimate, see chapter 10, step 7. Assessing the Reliability of a Cost Estimate In this chapter, the cost estimating best practices and the four characteristics of a high-quality cost estimate are presented as criteria— that is, the required or desired state or expectation with respect to a program or operation. Auditors can use these criteria to assess the reliability of a cost estimate and determine the thoroughness of an organization’s cost estimating guidance. 42 In addition, non-audit organizations can use the best practices and four characteristics to validate the quality of a program’s cost estimate. Cost Estimate Audit Criteria Auditors should identify criteria. Criteria provide a context for evaluating evidence and understanding the findings, conclusions, and recommendations included in an audit report. According to Government Auditing Standards, criteria represent the laws, regulations, contracts, grant agreements, standards, specific requirements, measures, expected performance, defined business practices, and benchmarks against which performance is compared or evaluated. 43 42From an auditing perspective, reliability means that data are reasonably complete and accurate, meet the intended purposes, and are not subject to inappropriate alteration. For more information, see GAO, Assessing the Reliability of Computer-Processed Data, GAO-09-365G, (Washington, D.C.: July 2009). 43GAO, Government Auditing Standards, GAO-18-568G (Washington, D.C.: July 2018). Page 197 GAO-20-195G Cost Estimating and Assessment Guide