=== page 1 === Text as published on gao.gov, https://www.gao.gov/products/b-112131, archived 2026-07-12. GAO published no original file for this decision. Rendered by Comptroller Desk. B-112131, Feb. 1, 1956 Number: B-112131 Date: 1956-02-01 B-112131, FEB. 1, 1956 TO HONORABLE LEWIS L. STRAUSS, CHAIRMAN, ATOMIC ENERGY COMMISSION: REFERENCE IS MADE TO THE COMMISSION'S LETTER OF JANUARY 17, 1956, RECEIVED JANUARY 19, 1956, REQUESTING OUR OPINION CONCERNING A PROPOSED CONTRACT BETWEEN THE COMMISSION AND OHIO VALLEY ELECTRIC CORPORATION (OVEC) FOR A SUPPLY OF 150,000 KW OF POWER TO THE PORTSMOUTH AREA OF THE COMMISSION. A TWENTY-FIVE YEAR POWER CONTRACT FOR 1,800,000 KW WAS ENTERED INTO BETWEEN OVEC AND AEC UNDER AUTHORITY CONTAINED IN THE SUPPLEMENTAL APPROPRIATION ACT, 1953, 66 STAT. 643, WHICH AUTHORITY SUBSEQUENTLY WAS EMBODIED IN SECTION 12 (D) OF THE ATOMIC ENERGY ACT OF 1946, AS AMENDED. SECTION 12 (D) OF THAT ACT, WITH CERTAIN ADDITIONS, BECAME SECTION 164 OF THE ATOMIC ENERGY ACT OF 1954, 68 STAT. 951. AT THE TIME THE EXISTING CONTRACT WAS MADE IT WAS CONTEMPLATED THAT THE OVEC PLANT CAPACITY WOULD BE 2,200,000 KW, OF WHICH 1,800,000 WERE TO BE FURNISHED TO AEC ON A FIRM BASIS. IT IS NOT EXPECTED THAT THE TOTAL PLANT CAPACITY WHEN COMPLETED WILL BE 2,354,000 KW, WHICH WILL LEAVE A MUCH GREATER PLANT CAPACITY AVAILABLE TO OVEC. THE CONTRACT NOW PROPOSED WOULD COVER THE FURNISHING TO AEC BY OVEC OF 150,000 KW OF THE ADDITIONAL POWER EXPECTED TO BE GENERATED, AND IS FOR A THREE-YEAR TERM, RENEWABLE FOR ADDITIONAL ANNUAL PERIODS AT RATES TO BE MUTUALLY AGREED UPON. SECTION 6.06 (B) OF THE PROPOSED CONTRACT PROVIDES THAT OVEC MAY TERMINATE THE AGREEMENT UNLESS IT SHALL HAVE RECEIVED, WITHIN 30 DAYS AFTER THE EFFECTIVE DATE THEREOF, AN OPINION OF THE COMPTROLLER GENERAL OF THE UNITED STATES TO THE EFFECT (1) THAT AEC HAD FULL POWER AND AUTHORITY TO ENTER INTO THE CONTRACT AND TO OBLIGATE THE UNITED STATES FOR ALL PAYMENTS TO OVEC CALLED FOR THEREUNDER, (2) THAT ALL ACTION NECESSARY UNDER SECTION 164 OF THE ATOMIC ENERGY ACT OF 1954 TO PERMIT THE CONTRACT TO BECOME EFFECTIVE HAS BEEN TAKEN, (3) THAT THE CONTRACT DOES NOT CONTRAVENE ANY OF THE PROVISIONS OF THE ATOMIC ENERGY ACT OF 1954, AND (4) THAT THE CONTRACT DOES NOT AFFECT THE EXISTING POWER CONTRACT BETWEEN OVEC AND AEC IN SUCH A MANNER AS TO CAUSE THAT EXISTING CONTRACT TO CONTRAVENE ANY OF THE PROVISIONS OF THE ATOMIC ENERGY ACT OF 1954. THE LETTER OF JANUARY 17, 1956, STATES THAT AN OPINION PRESENTLY IS REQUESTED ONLY ON POINTS 1, 3, AND 4 LISTED ABOVE, AND THAT IF OUR OPINION THEREON IS Page 1 of 3