=== page 1 === COMPTROLLER GENERAL OF THE UNITED STATES WASHINGTON, 0.C. 20548 January 31, 1978 IN REPLY REFER TO: B-11 5 3 9 8 The Honorable Melvin Price Chairman, Committee on Armed Services House of Representatives Dear Mr. Chairman: Pursuant to our responsibilities under the Impoundment Control Act of 1974, we have been closely monitoring Department of Defense (DOD) efforts to restart production activities in the B-1 bomber program. The purpose of this letter is to inform you of our latest findings and conclusions with respect to the program. On December 27, 1977, we sent a letter to the Secretary of Defense requesting a statement of DOD's progress and plans concerning B-1 bomber production activities. By letter dated January 18, 1978, copy enclosed, we received the DOD reply. Based upon the information we have obtained from DOD and our independent review of the situation, the pertinent facts may be summarized as follows. When the Congress failed to act favorably on the President's request to rescind $462 million in budget authority determined to be excess to DOD needs as a result of the decision to terminate production of the B-1 bomber, the funds were made available for obligation and DOD began taking steps to utilize the budget authority. Initially, DOD embarked on determining those actions needed to restart B-1 bomber production. To fund these "restart planning" activities, DOD released for expenditure $88,000 in the month of October and $100,000 in the month of November. The $188,000 was obtained from the $462 million proposed, but rejected, for rescission. The Department of the Air Force released $2 million during December for formulation of a formal proposal to begin B-1 production activities. And, for January 1978, the Department of the Air Force obligated $3.5 million for the program. DOD plans to further increase the amount of funding for proposal formulation for the month of February. The Department of Defense estimates that it will take about 3 months after the formulation of the proposal in order to definitize a contract for B-1 bomber production.