=== page 1 === Text as published on gao.gov, https://www.gao.gov/products/b-157360, archived 2026-08-24. GAO published no original file for this decision. Rendered by Comptroller Desk. B-157360, Aug. 11, 1965 Number: B-157360 Date: 1965-08-11 B-157360, AUG. 11, 1965 TO THE HONORABLE W. J. DRIVER, ADMINISTRATOR, VETERANS ADMINISTRATION: BY LETTER DATED JULY 28, 1965, REFERENCE 074B, THE DIRECTOR, SUPPLY MANAGEMENT SERVICE, HAS REQUESTED OUR DECISION CONCERNING THE ACTION TO BE TAKEN REGARDING A MISTAKE ALLEGED AFTER AWARD IN A BID SUBMITTED BY FRANK LILL AND SON, INC., UNDER INVITATION FOR BIDS NO. 65-39, ISSUED MAY 26, 1965, BY THE VETERANS ADMINISTRATION HOSPITAL, BATAVIA, NEW YORK. THE IFB, WHICH WAS MAILED TO SIX FIRMS AND PUBLICIZED IN SEVERAL AREAS, SOLICITED BIDS TO REPLACE A BOILER AT THE HOSPITAL. THE REPLACEMENT BOILER WAS TO BE BUILT TO CERTAIN SPECIFICATIONS AND INSTALLED BY THE CONTRACTOR IN ACCORDANCE WITH STATED REQUIREMENTS WITHIN 130 DAYS AFTER RECEIPT OF NOTICE TO PROCEED. LILL'S BID, THE ONLY BID RECEIVED IN RESPONSE TO THE IFB, WAS OPENED ON JUNE 15, AS SCHEDULED. UPON EVALUATION, THE BID WAS DETERMINED TO BE RESPONSIVE, AND THE BID PRICE OF $88,209 WAS FOUND TO BE REASONABLE. ACCORDINGLY, UPON DETERMINATION THAT LILL WAS A RESPONSIBLE BIDDER, ENGINEERING AND ADMINISTRATIVE PERSONNEL AT THE HOSPITAL RECOMMENDED TO THE HOSPITAL DIRECTOR THAT LILL BE AWARDED THE CONTRACT. BY LETTER DATED JUNE 25, THE CONTRACTING OFFICER NOTIFIED LILL OF THE AWARD AND MADE SPECIFIC REFERENCE TO THE 130-DAY PERFORMANCE PERIOD. LETTER DATED JUNE 30, LILL TOOK EXCEPTION TO THE PERFORMANCE PERIOD AND STATED THAT IT HAD NOT BEEN AWARE OF SUCH REQUIREMENT; ALSO, THAT AT LEAST 330 DAYS WOULD BE REQUIRED FOR THE CONTRACT WORK. IN A SUBSEQUENT DISCUSSION OF THE MATTER WITH THE PROCUREMENT OFFICIALS, LILL'S ATTENTION WAS DIRECTED TO THE 130-DAY PERFORMANCE PERIOD SPECIFIED IN ITS BID PAPERS. THEREAFTER, LILL FURNISHED A WORK SCHEDULE INDICATING THAT PERFORMANCE OF THE CONTRACT WOULD REQUIRE 362 DAYS, INCLUDING 30 DAYS FOR PREPARATION OF DRAWINGS AND 90 DAYS BEFORE SHIPMENT OF THE BOILER COULD BE EFFECTED TO THE CONTRACTOR, AS EVIDENCED BY A STATEMENT FROM THE BOILER MANUFACTURER. A REVIEW OF THE PROCUREMENT DISCLOSED THAT THE IFB WAS THE SECOND SOLICITATION FOR THE WORK IN QUESTION. IN THE FIRST SOLICITATION, BIDS HAD BEEN REQUESTED ON THE INSTALLATION OF A PACKAGE TYPE UNIT, FOR WHICH THE 130-DAY COMPLETION PERIOD WAS CONSIDERED ADEQUATE. IN THE SECOND SOLICITATION, HOWEVER, THROUGH ADMINISTRATIVE OVERSIGHT THE COMPLETION PERIOD WAS NOT INCREASED, ALTHOUGH IT IS CONCEDED THAT SUBSTANTIAL ADDITIONAL TIME WOULD BE REQUIRED FOR THE FABRICATION AND FIELD ERECTION OF A BOILER NOT OF STANDARD PRODUCTION DESIGN, AS CALLED FOR BY THE SECOND INVITATION. Page 1 of 3