=== page 1 === Text as published on gao.gov, https://www.gao.gov/products/b-160834, archived 2026-07-10. GAO published no original file for this decision. Rendered by Comptroller Desk. B-160834, Apr. 7, 1967 Number: B-160834 Date: 1967-04-07 B-160834, APR. 7, 1967 TO THE POSTMASTER GENERAL: REFERENCE IS MADE TO YOUR LETTER OF FEBRUARY 6, 1967, ASKING WHETHER PRIOR YEAR FUNDS PREVIOUSLY OBLIGATED FOR THE PURCHASE OF 3-WHEEL MAILSTERS MAY BE USED TO PROCURE REPLACEMENT 4-WHEEL VEHICLES; THE ORIGINAL CONTRACTOR'S RIGHT TO PROCEED HAVING BEEN TERMINATED BECAUSE OF FAILURE TO MEET SCHEDULED DELIVERIES. IT IS EXPLAINED THAT THE CARRIER MECHANIZATION PROGRAM BEGUN IN 1957 IS DIRECTED TO REDUCING FOOT DELIVERIES BY PROVIDING LETTER CARRIERS WITH MOTORIZED VEHICLES. AS PART OF THIS PROGRAM, A PURCHASE ORDER WAS ISSUED TO THE FEDERAL SUPPLY SERVICE, GENERAL SERVICES ADMINISTRATION, IN APRIL 1964, FOR 8,918 3-WHEEL MAILSTERS AND ANOTHER PURCHASE ORDER WAS ISSUED TO GSA IN JULY 1964, FOR AN ADDITIONAL 3,796 VEHICLES. THESE PURCHASE ORDERS CALLING FOR A TOTAL OF 12,714 VEHICLES WERE COMBINED BY GSA IN ONE INVITATION FOR BIDS. FOLLOWING NUMEROUS DELAYS ALSO EXPERIENCED WITH PRIOR REQUIREMENTS FOR FISCAL YEAR 1963, DUE TO SMALL BUSINESS SET-ASIDE DETERMINATIONS, A CONTRACT WAS AWARDED BY GSA ON JANUARY 27, 1965, TO THE UNIVERSAL FIBERGLASS CORPORATION FOR THE ENTIRE 12,714 UNITS AT $1,046 EACH TOTALING $13.3 MILLION. BASED UPON REPEATED DIFFICULTIES EXPERIENCED BY THE CONTRACTOR IN MEETING SCHEDULE PERFORMANCE, GSA, AFTER EXHAUSTING ALTERNATIVES, TERMINATED THE RIGHT OF UNIVERSAL FIBERGLASS TO PROCEED ON DECEMBER 2, 1966. IN THE INTERIM, IN ORDER TO MEET ADDITIONAL REQUIREMENTS FOR CARRIER VEHICLES, IT IS STATED THAT THE POST OFFICE DEPARTMENT PLACED AN ORDER WITH GSA FOR 2,500 UNITS ON MAY 17, 1965. FISCAL YEAR 1966 REQUIREMENTS FOR 4,941 UNITS WERE FORWARDED TO GSA ON JULY 9, 1965. THESE TWO QUANTITIES WERE ALSO COMBINED IN ONE INVITATION FOR BIDS AND THE CONTRACT WAS AWARDED BY GSA TO TUBULAR AIRCRAFT PRODUCTS COMPANY, INC., ON DECEMBER 10, 1965, THUS UTILIZING A SECOND SOURCE OF PRODUCTION FOR THE 7,441 UNITS. ON DECEMBER 20, 1965, DUE TO CONTINUED SLOW DELIVERIES OF NEW UNITS AND THE ACCELERATED DISPOSAL OF OLDER VEHICLES FOR SAFETY REASONS, THE POST OFFICE DEPARTMENT REQUESTED GSA TO PROCURE AN ADDITIONAL 4,000 UNITS, FOR WHICH A CONTRACT WAS AWARDED DECEMBER 30, 1965, TO WEST COAST MACHINERY, INC., AND THIS AWARD IS SAID TO HAVE DEPLETED REASONABLE (COST-WISE) SOURCES OF SUPPLY. AT THE TIME OF THE TERMINATION OF THE UNIVERSAL FIBERGLASS CONTRACT ON DECEMBER 2, 1966, THE CONTRACTOR HAD DELIVERED ONLY 4,224 OF THE 12,714 CONTRACTED UNITS. IN THIS CONNECTION, IT IS POINTED OUT THAT UNIVERSAL WAS NOT DEFAULTED AT AN EARLIER DATE BECAUSE OF THE LIMITED SOURCE OF SUPPLY FOR 3-WHEEL MAILSTERS AND Page 1 of 3