=== page 1 === Text as published on gao.gov, https://www.gao.gov/products/b-197256, archived 2026-07-12. GAO published no original file for this decision. Rendered by Comptroller Desk. B-197256, Nov 19, 1980 Number: B-197256 Date: 1980-11-19 B-197256, NOV 19, 1980 DIGEST: CITY OF OSCEOLA, MISSOURI, HAS NO LEGAL BASIS FOR RECOVERING FROM THE UNITED STATES AMOUNT OF INCREASED COSTS IT SUSTAINED BECAUSE OF EARLIER ERRONEOUS DETERMINATION OF ELIGIBLE GRANT COSTS BY ENVIRONMENTAL PROTECTION AGENCY, AS LONG AS FULL STATUTORY FEDERAL SHARE WAS PAID TO CITY WHEN GRANT WAS FINALLY MADE. CLAIM OF CITY OF OSCEOLA, MISSOURI: THE CITY OF OSCEOLA, MISSOURI, (CITY) HAS FILED A CLAIM AGAINST THE UNITED STATES ARISING FROM A SEWER AND WATER TREATMENT CONSTRUCTION PROJECT FUNDED BY A GRANT FROM THE UNITED STATES ENVIRONMENTAL PROTECTION AGENCY (AGENCY). THE CITY ARGUES THAT, BECAUSE OF IMPROPER AND UNJUSTIFIED RULINGS BY THE AGENCY, THE PROJECT HAS BEEN DELAYED MANY YEARS AND CONSEQUENTLY THE CITY MUST INCUR EXTRA COSTS EXCEEDING $200,000 TO COMPLETE THE PROJECT. THE CITY SEEKS TO RECOVER THESE ADDED COSTS FROM THE GOVERNMENT. WE FIND NO LEGAL BASIS FOR RECOVERY. THE FACTS AS PART OF ITS HARRY S. TRUMAN RESERVOIR PROJECT, IT BECAME NECESSARY FOR THE UNITED STATES ARMY CORPS OF ENGINEERS (CORPS) TO ACQUIRE INTERESTS IN LAND OWNED BY THE CITY, WHICH INCLUDED STREETS, SIDEWALKS, PARKS, SEWERS, AND A SEWAGE TREATMENT SYSTEM. ACCORDINGLY, ON JULY 30, 1970, THE CORPS AND THE CITY ENTERED INTO A CONTRACT UNDER WHICH THE CITY WAS TO CONVEY TO THE GOVERNMENT ITS INTERESTS IN THE LAND AND FACILITIES WITHIN THE RESERVOIR PROJECT BOUNDARIES, AND TO RELOCATE AND RECONSTRUCT THE VARIOUS CITY FACILITIES. IN RETURN, THE CORPS WAS TO PAY THE CITY $145,890 AS REIMBURSEMENT FOR RELOCATION OF THE SEWERS AND TREATMENT WORKS, AND $383,000 AS REIMBURSEMENT FOR THE REMAINING RELOCATION WORK. THE CONTRACT SPECIFIED THAT PAYMENT WOULD NOT BE MADE UNTIL THE RELOCATION WORK WAS COMPLETED. THE CREATION OF HARRY S. TRUMAN LAKE REQUIRED THE CITY TO CONSTRUCT TWO REPLACEMENT SEWER SYSTEMS. THE NORTH SIDE SYSTEM WAS COMPLETED IN EARLY 1973. THE SOUTH SIDE SYSTEM WAS DIVIDED INTO TWO SECTIONS TO SATISFY THE CLEAN WATER POLICIES OF THE STATE OF MISSOURI. SECTION I CONSISTED OF THE COLLECTOR SEWERS WHICH UNDER MISSOURI POLICIES WOULD NOT RECEIVE PRIORITY FOR FEDERAL GRANTS. SECTION II CONSISTED OF THE TREATMENT PLANT, LIFT STATIONS, FORCE MAINS, AND INTERCEPTOR SEWERS. IN AUGUST 1972 THE CITY APPLIED FOR A FEDERAL GRANT TO ASSIST IT IN THE CONSTRUCTION OF SECTION II. THE CITY ESTIMATES THAT IN EARLY 1974 THE TOTAL COST OF THE SOUTH SIDE SYSTEM WOULD HAVE BEEN $625,427, CONSISTING OF $184,291 FOR SECTION I, $376,961 FOR Page 1 of 6