Back to library

GAO decisions

[Question Concerning VA Delays in Obligating Funds]

GAO · Comptroller General Decision B-221412

GAO reviewed the Veterans Administration's (VA) delay in awarding certain construction contracts and the impoundment implications for obligations not incurred within specified time limits. GAO found that: (1) eight construction contracts had not been awarded by September 30, 1985, as required by the 1984 VA appropriation act; and (2) although VA did not award the contracts within the time limitations imposed by the appropriation act, its actions did not constitute an impoundment of budget authority.

Original file

Document preview

6 pages

Preview too small? Open the PDF in a new tab

6-page PDF. Opens in your phone's PDF viewer, where you can zoom and search.

Open PDF