B-226782, Oct 20, 1987
GAO · Comptroller General Decision B-226782
Claimant expended funds to purchase equipment pursuant to a letter of intent issued by the Department of the Army. At the time the letter of intent was signed, both parties contemplated execution of a formal contract shortly thereafter. However, for a variety of reasons, including uncertainty by the Army of the propriety of a contingent fee arrangement in which claimant was involved, the formal contract was never issued.