The Impact of Legislation on the CHAMPUS Reform Initiative Contract
GAO · Comptroller General Decision B-247119
1. An appropriations restriction ontained in the Department of Defense Appropriations Act, 1992, Pub. L. No. 102-172, requiring the extension of the CHAMPUS Reform In iative (CRr) contract, is in rect conflict with the ration Act Nati Fiscal Years 1992 and 1993, Pub. L. No. 102-190, which requires award of the CRr contract through standard procurement procedures. In response to a query from the Department, it is our view that the two statutes are irreconcilable and the Department should consider the most recent law, the Authorization Act, as controlling.