=== page 3 === whether the agency has followed the applicable statute and regulations. We will not second-guess the agency's determination that a given set of facts constitutes negligence unless the agency's finding can be said to lack a rational basis. Walter C. Stephenson, 65 Comp. Gen. 177, 179-80 (1986). The PCC assessed liability against Mr. Martino, the contracting officer, for failing to comply with the Federal Acquisition Regulation (FAR) requirement to conduct a market price study prior to extending a contract. FAR § 17.207. PCC also relied on its acquisition regulations, set out in 48 C.F.R. Part 35, which state that personal liability may be assessed against the individual who has made an unauthorized commitment of government funds. Panama Canal Commission Acquisition Rules (PAR) § 3501.602-3(b)(1). The basis for assessing the debt against Mr. Martino was the lack of evidence that he conducted or relied upon any kind of market survey in signing the contract extension as required by regulation. PCC's Inspector General found substantial evidence to support the conclusion that the extension was made with the knowledge that it was not supported by fact and was contrary to law or regulation. In particular, the contract extension was for $355/ton of liquid chlorine at a time when the producer price index was around $200/ton at the point of origin and the contractor was paying $165/ton to its supplier. The PCC concluded that since prices were considerably lower than the PCC was paying, Mr. Martino could not have conducted the required investigation of market prices prior to extending the contract. The PCC found that Mr. Martino's deliberate disregard of the FAR which required a market analysis made him responsible for the losses sustained by PCC as a result of his actions. Given the wide disparity in prices between what the PCC paid and what it might have paid for the commodity in question, we conclude that the PCC had a rational basis for the finding it reached. In collecting the debt through administrative offset under 31 U.S.C. § 3716, the PCC proceeded in accordance with 4 C.F.R. Part 102. The procedural rights to which Mr. Martino was entitled included written notice of the nature and amount of the debt, notice of the agency's intention to collect the debt by offset, an opportunity to inspect and copy agency records pertaining to the debt, the opportunity to obtain review within the agency of the determination of indebtedness, and the opportunity to enter into a written agreement with the agency to repay the debt. Our analysis of the record indicates that the PCC followed the applicable statute and regulations in administering the offset. Mr. Martino was provided notice of his indebtedness on March 2, 1994, PCC's intention to administratively offset the debt was provided in a June 14, 1994, letter to Mr. Martino; Mr. Martino was furnished documents on June 20, 1994; and a hearing was held with Mr. Martino present on October 18, 1994. Page 3 B-262168 715523