GraphicData, Inc.-Quantum Meruit Relief
GAO · Comptroller General Decision B-262251
A GPO contractor whose claim for unpaid services was denied by the contracting officer for failure to meet a contract provision requiring requests for billing adjustments to be submitted within 60 days of payment appeals the denial on equitable grounds. The claim is denied. To allow recovery based on the doctrine of quantum meruit or other equitable grounds would circumvent a provision of the contract, the purpose of which is to require requests for billing adjustments to be submitted to the contracting officer within a reasonable time after a payment is made.