=== page 1 === United States Government Accountability Office Washington, DC 20548 B-303906 December 7, 2004 The Honorable Orrin G. Hatch United States Senate Subject: National Parks Service Contract—Payments to Subcontractors Dear Senator Hatch: This responds to your letter, dated September 30, 2004, written on behalf of your constituent, Mr. E. Vernon Snow. According to your letter, Mr. Snow was a subcontractor for Pacific General, Inc. (PGI) and performed work at the Grand Canyon National Park under an Indefinite Delivery/Indefinite Quantity contract between PGI and the National Parks Service (Service). Because PGI has declared bankruptcy, leaving Mr. Snow with a difficult struggle against the contractor for compensation, Mr. Snow now seeks reimbursement from the Service. In your letter, you ask GAO to give authority to the Service to use appropriated funds to compensate unpaid subcontractors. The purpose of this letter is to advise you that the authority to settle Mr. Snow’s claim lies with the Department of the Interior, not GAO. Should Interior decide to settle the subcontractors’ claims, we would not object to Interior’s use of the remaining funds, estimated in the amount of $906,335, to pay Mr. Snow and others similarly situated. BACKGROUND Staff of the Rocky Mountain Region of Interior’s Solicitor’s Office, in informal telephone conversations, told us that between fiscal years 2002 and 2003, the Service awarded approximately 40 task orders to PGI. The contract was for construction projects in and around the Grand Canyon National Park. The Service believes that PGI subcontracted all of the projects to about 45 subcontractors, including Mr. Snow. The Service terminated the contract for default. By the time of termination, the Service had paid over $10 million to PGI for work performed. In April 2003, the Service terminated 17 task orders with PGI. In December 2003 and January 2004, the Service received payment invoices from PGI for work performed under the contract in the amount of $906,335. The Service has withheld payment from PGI on these specific invoices because of PGI’s default status of the contract task orders. Various