=== page 1 === Comptroller General of the United States United States Government Accountability Office Washington, DC 20548 Decision Matter of: Architect of the Capitol—Contract Ratification File: B-306353 Date: October 26, 2005 DIGEST The Architect of the Capitol may use appropriated funds to pay a contractor for services rendered pursuant to an unauthorized commitment. The Architect of the Capitol’s actions subsequent to learning of the unauthorized commitment constitutes a valid ratification. See generally B-259926, Mar. 31, 1995; B-251728.2, June 9, 1993. DECISION The Architect of the Capitol (AOC) has requested an advance decision under 31 U.S.C. § 3529 on whether it may use appropriated funds to pay a contractor for construction performed pursuant to directives issued without authority by an AOC employee. Because AOC validly ratified the unauthorized directives, it may use appropriated funds to pay the costs of the construction performed under those directives. See generally B-259926, Mar. 31, 1995; B-251728.2, June 9, 1993. BACKGROUND AOC is responsible for the maintenance and improvement of the U.S. Capitol Grounds. 40 U.S.C. § 5102. Pursuant to this responsibility, AOC is expanding the West Refrigeration Plant near the Capitol. The general contractor for this project is Hitt Contracting, Inc. (Hitt). Letter from Alan M. Hantman, Architect of the Capitol, to David Walker, Comptroller General of the United States, Sept. 19, 2005 (Hantman Letter). An AOC employee issued three directive letters to Hitt (directives) on March 30, 2004, January 25, 2005, and February 14, 2005, instructing Hitt to undertake work on the refrigeration plant project. The employee who issued the directives lacked the authority to do so. Id. Hitt, believing the directive letters to be authorized, began the requested work. Telephone interview with Cynthia Bennett, Director of Procurement, AOC, Oct. 4, 2005 (Bennett Interview 1). Upon learning that the directives were unauthorized,