Financial Crimes Enforcement Network--Obligations under a Cost-Reimbursement, Nonseverable Services Contract

GAO · Comptroller General Decision B-317139

A nonseverable services contract that is not separated for performance by fiscal year may not be funded on an incremental basis without statutory authority. Failure to obligate the estimated cost (or ceiling) of a nonseverable cost-reimbursement contract at the time of award violated the bona fide needs rule. Contract modifications to a cost-reimbursement contract increasing original ceiling are chargeable to appropriations available when the modifications were approved by the contracting officer.