=== page 30 === U.S. Chemical Safety and Hazard Investigation Board found that the CSB’s annual appropriation for fiscal year 2014 was only available for office space obligations for the agency’s needs of that fiscal year, and not for future fiscal years arising under the lease, in the absence of statutory authority. GAO determined that the CSB did not have statutory authority to use its annual appropriations for fiscal year 2014 for the needs of future fiscal years through a multi-year lease, despite the CSB’s statutory authority to enter into private leases as needed to support board operations. See 42 U.S.C. § 7412(r)(6)(N). At the time of execution, the CSB also did not yet have appropriations available for fiscal years 2016 through 2025. Therefore, GAO concluded, the CSB violated the ADA by incurring the subject ten-year lease obligation in advance of appropriations available for fiscal years 2016 through 2025. The CSB received a non-modified or “clean” audit opinion in fiscal year 2014, the year in which the CSB signed the lease, when the ADA violation occurred. For each fiscal year from 2016 through 2023, the CSB similarly received non-modified audit opinions. However, the CSB received a qualified audit opinion in FY 2024 based on this issue. No disciplinary action for this matter was taken against the former contracting officer, former financial management officials, or other former senior agency leaders who were responsible for this violation. These CSB employees were the ones who negotiated, advised on, approved, and signed the lease agreement; however, they all are no longer employed by the CSB. The CSB has also determined that these responsible parties appear to have had no knowing or willful intent to violate the ADA and were unaware of the impact that the bona fide needs rule and the recording statute should have had in limiting the CSB’s ability to sign the ten-year lease for its headquarters space back in 2014. Despite disagreement with some underlying factual assertions in the GAO opinion, the CSB is taking steps to ensure that safeguards are in place to prevent recurrence of the circumstances presented in this matter, and to avoid any new ADA violations with respect to private lease agreements. The CSB has been consulting with the General Services Administration (GSA) about the CSB’s office space needs in Washington, D.C. The CSB also has been consulting with the Office of Management and Budget (OMB) to ensure compliance with federal appropriations laws relevant to this matter. In addition, the CSB is taking steps to ensure that relevant agency staff are trained in the requirements of the ADA, including staff in the CSB’s Office of Contracting, Office of Financial Operations, and Office of General Counsel. This training includes, but is not limited to, issues related to a federal agency’s responsibilities and limitations when leasing private office space. Last, in accordance with the Federal Financial Management Improvement Act of 1996 (FFMIA), the CSB acknowledges the agency has the responsibility for establishing and maintaining effective internal controls to meet the objectives delineated in the FFMIA. The CSB believes that its internal controls are adequate with respect to supporting the effectiveness and efficiency of operations, and sufficient to ensure the reliability of financial reporting and to ensure compliance with applicable laws and regulations. These controls include, but are not limited to, financial internal controls, procurement internal controls, human resources internal controls, information technology internal controls, and 2