  1. GAO decisionsMarch 20, 1984

    [Request for Concurrence in Navy Interpretation of Termination Liability Obligations]

    GAO Comptroller General Decision B-174839

    The Navy requested GAO concurrence in its interpretation of a 1983 supplemental appropriations act provision concerning the recording of obligations for termination liability for the TAKX and T-5 ship leasing programs. GAO agreed with the Navy's view that the provision constitutes contract authority to cover all but 10 percent of the termination liability arising from the ship charters.

  2. GAO decisionsMarch 19, 1984

    [Request for Clarification and Expansion of GAO Views on the Chadha Decision]

    GAO Comptroller General Decision B-196854.3

    Pursuant to a congressional request, GAO discussed the impact of the Chadha decision on the appropriations process. GAO focused on the implications of the decision for reprogrammings, committee vetoes, committee approvals, deferrals, and rescissions. GAO suggested that the use of line item appropriations and riders on appropriations acts, rather than after the fact involvement by Congress, would enable Congress to limit executive branch authority in a constitutionally permissible fashion.

  3. GAO decisionsMarch 16, 1984

    [Request for Advance Decision]

    GAO Comptroller General Decision B-211700

    The Uniformed Services University of the Health Sciences requested an advance decision as to whether appropriated funds may be used for expenses related to the University's annual graduation ceremony. GAO determined that funds allotted to the University from its congressional appropriation are available for all of its functions, including its graduation ceremony. GAO concluded that expenditures for the rental of academic regalia for invited guests, military students, and faculty were necessary to carry out the objectives of the University's appropriation.

  4. GAO decisionsFebruary 17, 1984

    B-212337 February 17, 1984

    GAO Comptroller General Decision B-212337

    1. Request for relief of Army disbursing officer under 31 U.S.C. Sec. 3527(c) for deficiency in his accounts of $46 resulting from two incorrect payments may not be granted where record fails to show that officer was not personally responsible for the improper payment and that he properly supervised his subordinates and maintained adequate system of procedures and controls. 2. Relief for erroneous per diem payments to Republic of Philippines trainees not granted.

  5. GAO decisionsFebruary 2, 1984

    B-214086, Feb 2, 1984, Office of General Counsel

    GAO Comptroller General Decision B-214086

    MR. EDWARD P. GREENBERG CHIEF, DIVISION OF FINANCE BUREAU OF LAND MANAGEMENT DEPARTMENT OF THE INTERIOR: THIS IS IN RESPONSE TO YOUR REQUEST (REFERENCE 1385 (822)) THAT TOM WELCH, AN EMPLOYEE OF THE BUREAU, BE RELIEVED OF LIABILITY FOR THE LOSS OF $159.68 IN IMPREST FUNDS. FOR THE REASON EXPLAINED BELOW, WE ARE REFERRING THIS REQUEST TO YOUR OFFICE FOR ADMINISTRATIVE ACTION. GAO HAS DELEGATED AUTHORITY TO AGENCY AND DEPARTMENT HEADS TO ADMINISTRATIVELY RESOLVE CERTAIN IRREGULARITIES IN THE ACCOUNTS OF ACCOUNTABLE OFFICERS.

  6. GAO decisionsFebruary 1, 1984

    B-214058 February 1, 1984

    GAO Comptroller General Decision B-214058

    This is in response to your letter dated December 22, 1983, written jointly with Senator Packwood, requesting the opinion of this Office as to whether the last paragraph of Chapter XI of Title I of the Supplemental Appropriations Act, 1983, Pub. L. No. 98-63, 97 Stat. 301, 343-44, constitutes permanent legislation. This provision of the Act prohibits under certain circumstances the retroactive application of section 44C of the Internal Revenue Code, 26 U.S.C. Sec. 44C (1982), relating to energy tax credits.

  7. GAO decisionsJanuary 8, 1984

    B-210518 January 8, 1984

    GAO Comptroller General Decision B-210518

    This is in response to your inquiry concerning the propriety of the Environmental Protection Agency (EPA) contracting with the law firm of Ropes and Gray to assist EPA in dealing with legal issues arising from the Congressional citation of then-Administrator Anne M. Burford for contempt. The contempt citation resulted from Mrs. Burford's refusal, stated to be at the direction of the President, to provide certain confidential enforcement documents to the Subcommittee on Investigation and Oversight of the House Committee on Public Works and Transportation.

  8. GAO decisionsJanuary 3, 1984

    B-211323, Jan 3, 1984

    GAO Comptroller General Decision B-211323

    FUNDS APPORTIONED TO STATES IN ACCORDANCE WITH SECTION 304 OF THE PUBLIC WORKS AND ECONOMIC DEVELOPMENT ACT OF 1965, AS AMENDED, AND RECOVERED DUE TO COST UNDERRUNS MAY BE REOBLIGATED BY THE STATES FOR PURPOSES WITHIN THE SCOPE OF THE AUTHORIZING STATUTE. ONCE APPORTIONED TO THE STATES, SECTION 304 FUNDS TAKE ON THE CHARACTERISTICS OF NO-YEAR MONEY AND REMAIN AVAILABLE UNTIL EXPENDED.

  9. GAO decisionsDecember 23, 1983

    B-209649, Dec 23, 1983

    GAO Comptroller General Decision B-209649

    1. NEITHER GRANT AGREEMENT BETWEEN AID AND BOLIVIA NOR CONTRACT BETWEEN BOLIVIA AND PRIVATE COMPANY TO CARRY OUT GRANT MAKES AID LIABLE TO PAY AMOUNTS AWARDED BY BOLIVIAN AND UNITED STATES COURTS AS LABOR BENEFITS RESULTING FROM COMPANY'S TERMINATING ITS EMPLOYMENT CONTRACTS. 2. AFTER AID DISCONTINUED MAKING GRANT PAYMENTS TO PRIVATE COMPANY UNDER GRANT AGREEMENT BETWEEN AID AND BOLIVIA, AND PRIVATE COMPANY TERMINATED EMPLOYMENT CONTRACTS, SEVERAL OF COMPANY'S EMPLOYEES SUED COMPANY FOR LABOR BENEFITS.

  10. GAO decisionsDecember 23, 1983

    [Query Concerning Advance Payment for Interlaboratory Comparison Survey Program]

    GAO Comptroller General Decision B-210719

    An Army finance and accounting officer requested a decision to resolve an internal staff dispute concerning whether the Army can properly pay in advance for subscriptions to the college Interlaboratory Comparison survey program to satisfy quality control and accreditation requirements. The program provides subscribers with printed evaluations based upon participant input and survey kits that can be used to perform tests to obtain input data.

  11. GAO decisionsDecember 21, 1983

    B-212515 December 21, 1983

    GAO Comptroller General Decision B-212515

    F. P. Cantrell, Manager Accounting Division Federal Aviation Administration Department of Transportation P.O. Box 92007 - Worldway Postl Center Los Angeles, California 90009 Dear Mr. Cantrell: This responds to a request from your office that relief be granted to Donna F. Tellgren, a Class "B" Cashier with the Federal Aviation Administration (FAA), for the physical loss of $678.86. For the following reasons, the requested relief is granted.

  12. GAO decisionsDecember 15, 1983

    B-211660, Dec 15, 1983, Office of General Counsel

    GAO Comptroller General Decision B-211660

    THIS IS IN RESPONSE TO YOUR LETTER DATED APRIL 27, 1983 (REFERENCE:FINCY- D KINCAID, K. T. (3855)) REQUESTING THAT WE GRANT RELIEF TO LIEUTENANT COLONEL K. T. KINCAID, FINANCE AND ACCOUNTING OFFICER AT THE U.S. ARMY ARMOR CENTER AND FORT KNOX, KENTUCKY, FROM LIABILITY FOR A DEFICIENCY IN HIS ACCOUNTS OF $56.00 RESULTING FROM AN INCORRECT PAYMENT.